Ques1. A TAKES 6 DAYS LESS THAN B TO FINISH A PIECE OF WORK IF BOTH A & B TOGETHER CAN FINISH IT IN 4 DAYS ,FIND THE TIME TAKEN BY B TO FINISH THE WORK.FIND ITS SOLUTION ONLY IN quadratic equation form by factorization method
Ques2. TWO CIRCLES TOUCH EXTERNALLY.THE SUM OF THEIR AREA IS 130π SQUARE CM & DISTANCE BETWEEN THEIR CENTRES IS 14 cm .FIND THE RADII OF THE CIRCLES ?FIND ITS SOLUTION ONLY IN quadratic equation form by factorization method
Ques2. TWO CIRCLES TOUCH EXTERNALLY.THE SUM OF THEIR AREA IS 130π SQUARE CM & DISTANCE BETWEEN THEIR CENTRES IS 14 cm .FIND THE RADII OF THE CIRCLES ?FIND ITS SOLUTION ONLY IN quadratic equation form by factorization method
-
1/a + 1/b = 1/4
1/(b - 6) + 1/b = 1/4
4b + 4b - 24 = b^2 - 6b
b^2 - 14b + 24 = 0
(b - 2)(b + 12) = 0
b = 2 , 12 => reject b = 2 , (less than 6)
b = 12 days
2) let the radii be R and r:
R + r = 14 cm => r = 14 - R
A + a = 130π cm^2
πR^2 + πr^2 = 130π
R^2 + (14 - R)^2 = 130
R^2 + (196 - 28R + R^2) = 130
2R^2 - 28R + 196 - 130 = 0
R^2 - 14R + 33 = 0
(R - 3)(R - 11) = 0
R = 3 , 11 cm
r = 11 , 3 cm
1/(b - 6) + 1/b = 1/4
4b + 4b - 24 = b^2 - 6b
b^2 - 14b + 24 = 0
(b - 2)(b + 12) = 0
b = 2 , 12 => reject b = 2 , (less than 6)
b = 12 days
2) let the radii be R and r:
R + r = 14 cm => r = 14 - R
A + a = 130π cm^2
πR^2 + πr^2 = 130π
R^2 + (14 - R)^2 = 130
R^2 + (196 - 28R + R^2) = 130
2R^2 - 28R + 196 - 130 = 0
R^2 - 14R + 33 = 0
(R - 3)(R - 11) = 0
R = 3 , 11 cm
r = 11 , 3 cm
-
You are always welcome my Friend.
Report Abuse
-
1) Let B alone take X days to finish a piece of work.
A alone will take (X - 6) days to finish the same piece of work.
In 1 day B alone will finish 1 / X of the work and A alone in 1 day will finish 1 / ( X - 6) of the work.
Since together they finish the work in 4 days , together in 1 day they will finish 1/4 of the work
i.e. 1 / X + 1 / ( X -6) = 1/4
MULTIPLY BOTH SIDES BY X (X-6)*4
4( X -6) + 4X = X ( X -6)
4X -24 + 4X = X^2 -6X
X^2 -14X + 24 = 0
( X -12) ( X - 2) = 0
X = 12 Or 2
X cannot be 2
ANSWER B takes 12 days and A takes 6 days
CHECK
1/12 + 1/6 = ( 1 +2) /12 = 3/12 = 1/4
2) Let the radius of first circle be X cm
Radius of the second circle will be (14 - X ) cm
Sum of the Area of the circles = pi X^2 + pi ( 14 - X)^2
A alone will take (X - 6) days to finish the same piece of work.
In 1 day B alone will finish 1 / X of the work and A alone in 1 day will finish 1 / ( X - 6) of the work.
Since together they finish the work in 4 days , together in 1 day they will finish 1/4 of the work
i.e. 1 / X + 1 / ( X -6) = 1/4
MULTIPLY BOTH SIDES BY X (X-6)*4
4( X -6) + 4X = X ( X -6)
4X -24 + 4X = X^2 -6X
X^2 -14X + 24 = 0
( X -12) ( X - 2) = 0
X = 12 Or 2
X cannot be 2
ANSWER B takes 12 days and A takes 6 days
CHECK
1/12 + 1/6 = ( 1 +2) /12 = 3/12 = 1/4
2) Let the radius of first circle be X cm
Radius of the second circle will be (14 - X ) cm
Sum of the Area of the circles = pi X^2 + pi ( 14 - X)^2
12
keywords: equation,method,the,factorization,by,Solve,quadratic,Solve the quadratic equation by factorization method