two people paint a wall in 3days
if we add 3 other people
this wall will be painted for......?(days)
if we add 3 other people
this wall will be painted for......?(days)
-
One person paints 1/6th of the wall per day
5/6th of the wall is painted per day if we have 5 people
1 / (5/6) => 6/5
1.2 days
5/6th of the wall is painted per day if we have 5 people
1 / (5/6) => 6/5